Data Center Case · Source records

Public Records & Meeting Library

A curated guide to the documents behind Cle Elum's data-center discussion, including city meetings, development agreements, land-use decisions, environmental records, and independent analysis.

Compiled November 4, 2026 · Return to the Data Center Case

How to use this library: Documents are linked to issuing agencies or their public meeting systems whenever available. Some links open the city’s document collection or CivicClerk portal rather than one fixed PDF. A secondary index is provided where useful for locating a particular meeting. This page does not claim that every underlying record has been uploaded or independently reproduced here.

Status matters: A draft minute, an agenda, a public comment, an applicant claim, a planning condition and a final city decision are different types of evidence. Links and document availability may change. For the authoritative record, consult the issuing agency.

Source category

Meetings, agendas and minutes

Public deliberations, procedural actions and the committee's evolving work plan. The October 21 record is still labeled draft in the November 4 packet.

September 8, 2026 City of Cle Elum · City Council

City Council: Data Center Moratorium Hearing

Minutes indexed

Planning Director Shannon Johnson said the municipal code did not address data centers. The hearing record does not, by itself, determine the permitted use of the Blue Fern parcel.

October 21, 2026 City of Cle Elum · Advisory Committee

Data Center Advisory Committee: first meeting agenda

Published agenda

Introductions, public comment, draft work plan, initial priorities and questions on land use, environmental effects and economics.

October 21, 2026 City of Cle Elum · Advisory Committee

Advisory Committee: draft meeting minutes

DRAFT, not confirmed approved

Two-page draft minutes appear on pages 3–4 of the November 4 packet. Chair Harper distinguishes possible future committee recommendations from the existing Bullfrog Flats development agreement; the minutes also summarize residents' comments and the proposed work plan.

November 4, 2026 City of Cle Elum · Advisory Committee

Advisory Committee: agenda and packet

Agenda and packet

Agenda includes October 21 draft minutes, definitions and a Planning Director report. The four-page packet reviewed contains the agenda and draft minutes, not a separate written Planning Director report. Later materials may be published.

Source category

Development agreements and planning records

Historical rights, amendments, plats and conditions that must be distinguished from a parcel-specific approval for a data center.

2017 and March 2025 City of Cle Elum · Planning

Subsequent Development Agreement amendments

Amendments documented by city

The city identifies a 2017 amendment and a 2025 Second Amendment transferring the agreement to Bullfrog Flats, LLC, with conditional extension provisions. Actual text controls; vesting and applicability to a data center are unresolved in this library.

January–March 2025 City of Cle Elum · Planning

Master Plat staff report, conditions and notice of decision

City planning record

Includes Master Plat conditions; Conditions 75 and 76 address noise-sensitive receiving areas such as homes and school property. These are broader master-plan conditions, not proof of specific data-center construction approval.

Source category

Environmental and utility records

State records and standards relevant to generator emissions, noise and historical PSE activity.

October 17, 2017 City of Cle Elum / Washington Ecology SEPA Register

PSE Cascade Modular Data Center: SEPA DNS

Historical environmental-review determination

PSE's separate 2017 modular data-center proposal at 1980 SR 903. The city acted as lead agency; this does not authorize Blue Fern's proposed 2026 facility.

January 29, 2018 Washington Department of Ecology

PSE Cle Elum generator air approval

Historical approval order 18AQ-C225

Air-quality approval for backup-generation equipment serving PSE's separate project. No presumption that the order applies to a different development.

Current rules Washington Department of Ecology / Washington Administrative Code

Air pollution reviews and statewide noise rules

Regulatory resources

Background requirements for generator permitting and toxic air-pollution review, alongside state environmental noise standards. Which thresholds apply depends on project design and receiving property.

Source category

Independent research, not government findings

WHCER's related interpretive and scenario materials. Their conclusions and assumptions should be tested against original sources.

October 2026 Karl Ohlemann · Independent analysis

Public Discussion Brief (25-page PDF)

Commentary and illustrative analysis

Economic-development framing, potential public benefits, risks and questions. Not a city finding or land-use determination.

October 2026 Karl Ohlemann · Independent analysis

Preliminary Economic & Fiscal Assessment (31-page PDF)

Scenario model, not project forecast

Fiscal and utility-tax scenarios with assumptions and sensitivities. Does not resolve permitted uses, official tax values or project-specific engineering.

Help improve the record

Missing a document or correction?

If you have a source document, subsequent approved minutes, a written Planning Director analysis, a permit decision, or an accurate correction, please share the agency name, document title, meeting date and source URL. Do not send private correspondence or confidential records. We will identify later updates with their dates rather than silently revise historical entries.